Quick answer: Compare plumbing bids by matching the work included—not just the total price. Verify required credentials and insurance, identify exclusions, and get payment terms, change-order procedures and warranties in writing. Consumer agencies recommend multiple written estimates and caution against automatically choosing the lowest bidder. (consumer.ftc.gov)
For U.S. homeowners. State examples were checked November 22, 2026. Licensing, contracts and payment rules depend on your location and project; this guide is general information, not legal advice.
1. Give every plumber the same written scope
Start with a short project description that you send to each bidder. State what you want repaired or replaced, where it is, and what you expect the finished job to include. Washington’s Department of Labor & Industries recommends defining the project before seeking bids and comparing scope, warranties, references, completion dates and price together. (lni.wa.gov)
Use this practical request checklist:
- Work boundaries: Which fixtures, pipe sections or connections are included?
- Materials: What pipe material, fixture brand and model, valves or equipment are proposed?
- Labor: What installation, removal and testing work is included?
- Access: Who opens walls, floors, cabinets or paving?
- Completion: Who restores those surfaces and removes debris?
- Timing: When could work begin, and when is completion expected?
Detailed descriptions of materials, responsibilities and cleanup are consistent with California’s contractor-contract guidance. Ask for separate prices for meaningful alternatives rather than accepting an unexplained substitution. (cslb.ca.gov)
Also ask whether the proposed charge is fixed for a defined scope or calculated from labor time and materials. For any variable-price work, request the rates, minimum charges, markups and authorization process. Do not assume that every document titled “estimate” promises the same price protection; contract requirements vary by state. (consumer.ftc.gov)
2. Verify credentials with the authority that regulates the work
Ask your local building department or consumer-protection agency which credentials your project requires. Then check the contractor’s current record with the issuing authority. The FTC notes that licensing requirements vary and that registration can differ substantially from a detailed qualification process. (bulkorder.ftc.gov)
For each bidder, record:
- Legal business name and any trading name.
- License or registration number.
- Current status and expiration date, if shown.
- Whether the credential covers the proposed work.
- Relevant public disciplinary information.
Check the business named on the proposal, not just a similarly named company. The CFPB recommends independently looking up the number and checking public disciplinary complaints. (consumerfinance.gov)
Washington example: L&I requires a plumbing contractor license to advertise, bid on or perform plumbing work. A general contractor wishing to perform plumbing work must also hold that plumbing contractor license; general contractor registration alone is not sufficient. This is a Washington rule, not a nationwide requirement. (lni.wa.gov)
Finally, call references for comparable projects. Ask whether the final bill matched the agreed scope and how the contractor handled unexpected costs. The FTC recommends asking past customers about timing, satisfaction, cleanup and cost surprises. (bulkorder.ftc.gov)

3. Check insurance documents—not just an “insured” claim
Request current insurance documentation before committing. California’s Department of Insurance advises homeowners to ask about general liability and workers’ compensation insurance, obtain a certificate showing the insurer, policy number and limits, and verify the information directly with the insurer. (insurance.ca.gov)
Use the certificate as a verification checklist:
- Does the insured business match the contractor you are hiring?
- Are the policy dates current for the planned work?
- What coverage and limits are listed?
- Who can confirm the information?
- Will subcontractors participate, and have their required credentials and insurance been checked?
The FTC specifically recommends checking subcontractors’ current insurance and licenses where required. (bulkorder.ftc.gov)
Do not apply a blanket workers’ compensation assumption everywhere. Washington’s guidance, for example, distinguishes businesses employing workers from owner-operators without employees. Ask the appropriate authority how any claimed exemption applies. (lni.wa.gov)
4. Resolve permits, restoration and other exclusions
Ask every bidder to label each major item included, excluded, allowance or not yet determined. A blank should trigger a question, not an assumption.
Confirm permit requirements with the local permitting office. Put responsibility for obtaining permits, paying fees and coordinating inspections in writing. The CFPB identifies permit responsibility as a question to settle before hiring, while CSLB’s homeowner checklist specifically asks whether permit fees are included. (consumerfinance.gov)
For plumbing work, use these prompts to clarify the proposed scope:
| Work area | Question to resolve |
|---|---|
| Wall or floor access | Is opening included? Who closes and finishes it? |
| Excavation | What digging, backfill and surface restoration are included? |
| Equipment replacement | Are removal, hauling and disposal included? |
| Testing and inspection | What testing and inspection coordination are included? |
| Finishes | Does “patching” include texture, primer and paint? |
| Cleanup | What debris removal and final cleaning are promised? |
These are questions to ask—not claims that every project needs every item. Written responsibility for materials, permits and cleanup helps define what the contractor will deliver. (cslb.ca.gov)
An allowance is a budget amount for something not yet selected or finalized. Ask how an allowance changes the total, including taxes and markups. CSLB’s contract guide illustrates adjusting allowance differences through a written change order. (cslb.ca.gov)

5. Use a three-bid worksheet and compare equivalent totals
Copy this worksheet and complete it from the written proposals. Enter “unresolved” wherever an answer is missing. It brings together the scope, credential, insurance, payment and warranty checks recommended by consumer agencies. (consumerfinance.gov)
| Comparison item | Bid A | Bid B | Bid C |
|---|---|---|---|
| Business name; credentials verified on | ___ | ___ | ___ |
| Insurance checked; policy dates | ___ | ___ | ___ |
| Exact work boundaries | ___ | ___ | ___ |
| Materials and equipment models | ___ | ___ | ___ |
| Labor and pricing basis | ___ | ___ | ___ |
| Permits, fees and inspections | ___ | ___ | ___ |
| Access and restoration | ___ | ___ | ___ |
| Removal and cleanup | ___ | ___ | ___ |
| Exclusions and allowances | ___ | ___ | ___ |
| Start, completion and water interruptions | ___ | ___ | ___ |
| Deposit and payment milestones | ___ | ___ | ___ |
| Written change-order process | ___ | ___ | ___ |
| Workmanship and product warranties | ___ | ___ | ___ |
| Quoted total, including stated taxes | ___ | ___ | ___ |
| Written additions needed for equal scope | ___ | ___ | ___ |
| Comparable total; unresolved risks | ___ | ___ | ___ |
Worked example—hypothetical U.S. dollars, not market pricing or actual contractor quotes:
Suppose three proposals cover the same plumbing installation, but their surrounding work differs.
| Comparison | Bid A | Bid B | Bid C |
|---|---|---|---|
| Initial proposal | $4,200 | $4,850 | $5,100 |
| Permit and inspection fees omitted | $250 | Included | Included |
| Wall restoration omitted | $600 | Included | Included |
| Hauling omitted | $150 | Included | Included |
| Equal-scope total | $5,200 | $4,850 | $5,100 |
Bid A initially appears $650 cheaper than Bid B. With the hypothetical omitted work added, it becomes $350 more expensive.
For a real comparison, replace every illustrative addition with a written price from the responsible provider. If restoration remains unpriced, record “restoration unresolved” rather than manufacturing a complete total. An incomplete bid is not yet a comparable bid.
6. Link payments to defined milestones and local rules
Request a schedule stating the amount due and the work or delivery that triggers each payment. Possible milestones to discuss include completed installation, required inspections and agreed restoration. Avoid dates alone as payment triggers when the contract can instead identify completed work. The FTC recommends making progress payments contingent on defined amounts of work. (bulkorder.ftc.gov)
California example: For applicable home-improvement contracts, CSLB states that the down payment cannot exceed $1,000 or 10% of the contract price, whichever is less. Its consumer guide identifies a limited exception for qualifying licensees with blanket performance and payment bonds. Special-order materials do not themselves create an exception. Verify whether the rule and any exception apply to your contract. (cslb.ca.gov)
Do not transplant that limit to another state. Check your local consumer agency’s rules. The FTC advises against paying the whole project price upfront or making final payment before the work is done and satisfactory. (consumer.ftc.gov)
Keep receipts and compare each payment request against both the schedule and documented progress. (consumerfinance.gov)
7. Agree on change orders before unexpected work begins
Ask how the plumber will document a concealed problem, price additional work and obtain your approval.
Request a change-order form that records:
- The condition discovered and proposed response.
- Work added or removed.
- The price increase or credit.
- Any revised payment milestone.
- The effect on completion and water availability.
- Approval by both parties before the changed work begins.
CSLB’s guidance requires written, signed change orders before changes to covered California home-improvement work. Its contractor guide identifies scope, price and payment-schedule effects as essential details. Use this as a comparison checklist elsewhere, while checking local requirements. (www2.cslb.ca.gov)
For your own review, separate three questions: Was the item already included? Was it excluded? Or is it genuinely newly discovered? Ask the contractor to point to the relevant scope language before approving an extra charge.
Keep approved changes with the original agreement. The FTC recommends retaining contracts, change orders, correspondence and payment records together. (bulkorder.ftc.gov)
8. Separate workmanship and product warranties before signing
Request two sets of terms: the contractor’s warranty for its work and any manufacturer warranty for installed products. CSLB advises obtaining both in writing and identifying the covered work and duration. (cslb.ca.gov)
Do not compare duration alone. Ask:
- Who handles the claim?
- When does coverage begin?
- What is excluded?
- Are troubleshooting, travel, removal and reinstallation covered?
- Does a replacement part come with any labor coverage?
- What maintenance or registration conditions apply?
Treat those as questions to resolve from the actual documents, not assumed benefits. FTC guidance calls for identifying who honors each warranty, its duration and its limitations. (bulkorder.ftc.gov)
Before signing, resolve blank spaces, conflicting totals and verbal promises missing from the paperwork. Before final payment, check the completed scope, cleanup and written warranties against the agreement. (consumer.ftc.gov)
Choose only after you can explain why one proposal offers the better combination of verified qualifications, complete scope, manageable uncertainty and clear terms—not simply the lowest opening number.